File #: RS-23-146    Version: 1 Name: Professional Service Agreement-Garver LLC
Type: Resolution Status: Passed
File created: 8/14/2023 In control: City Council
On agenda: 9/26/2023 Final action: 9/26/2023
Title: Consider a memorandum/resolution approving a Professional Services Agreement with Garver, LLC, for design of the Passenger Terminal Mechanical Improvements Project at Killeen-Fort Hood Regional Airport, in the amount of $293,200.
Sponsors: Aviation Department
Attachments: 1. Agreement, 2. Certificate of Interested Parties, 3. Presentation
Title

Consider a memorandum/resolution approving a Professional Services Agreement with Garver, LLC, for design of the Passenger Terminal Mechanical Improvements Project at Killeen-Fort Hood Regional Airport, in the amount of $293,200.

Summary

DATE: September 19, 2023

TO: Kent Cagle, City Manager

FROM: Mike Wilson, Executive Director of Aviation

SUBJECT: Professional Services Agreement with Garver, LLC

BACKGROUND AND FINDINGS:

The Bipartisan Infrastructure Law (BIL) signed into law on November 15, 2021, provides $15 billion in Airport Infrastructure Grants (AIG) over a five (5) year period for airport-related projects as defined under the existing Airport Improvement Grant and Passenger Facility Charge (PFC) criteria.

The City has been offered a Federal Aviation Administration (FAA) BIL Airport Infrastructure Grant in the amount of $267,322 to fund 90% of the Design Services, Project Administration, and Bidding Services of the Passenger Terminal Mechanical Improvements Project at the Killeen-Fort Hood Regional Airport (KFHRA). Matching funds, in the amount of $29,703, will come from the FAA PFC Application that was approved by the FAA on February 16, 2023.

The project is comprised of various components including replacing the baggage claim carousels and associated belt system; upgrading the baggage system control hardware and software; replacing the preconditioned air units on boarding bridges 1 and 6; and replacing the terminal emergency generator.

Staff has negotiated a professional services agreement with Garver, LLC, in the amount of $293,200, for the project administration, design services, and bidding services for the Passenger Terminal Mechanical Improvements project at KFHRA.

THE ALTERNATIVES CONSIDERED:

1. Disapprove the agreement.
2. Approve the agreement.

Which alternative is recommended? Why?

Alternative 2 is recommended because:

1. The Garver team is the Airport engineer of record and was selected via a competitive process.
2. ...

Click here for full text