File #: RS-16-103    Version: 1 Name: US 190-FM 2410-ROSEWOOD DR CO#61
Type: Resolution Status: Passed
File created: 8/1/2016 In control: City Council
On agenda: 9/13/2016 Final action: 9/13/2016
Title: Consider a memorandum/resolution authorizing Change Order No. 61 with James Construction Group, LLC to the US 190/FM 2410/Rosewood Drive project.
Sponsors: Public Works Department, Transportation Division
Indexes: US190-Rosewood-FM2410
Attachments: 1. Council Memorandum, 2. Change Order, 3. Change Order Worksheet, 4. Change Order History, 5. Certificate of Interested Parties
Related files: RS-16-137
TITLE

Consider a memorandum/resolution authorizing Change Order No. 61 with James Construction Group, LLC to the US 190/FM 2410/Rosewood Drive project.

SUMMARY

AGENDA ITEM

AUTHORIZE CHANGE ORDER NO. 61 TO THE US 190/FM 2410/ROSEWOOD DRIVE PASS-THROUGH FINANCING CONTRACT WITH JAMES CONSTRUCTION GROUP, LLC.

ORIGINATING DEPARTMENT

PUBLIC WORKS - TRANSPORTATION DIVISION

BACKGROUND INFORMATION

On January 8, 2013 (CCM/R 13-001R), the City Council awarded a construction contract to James Construction Group, LLC for the Pass Through Financing (PTF) Project, US 190/FM 2410/ Rosewood Drive. This project included the construction of an overpass at the intersection of US 190 and Rosewood Drive, the widening of FM 2410, and the construction of Rosewood Drive from US 190 to Fawn Drive.

DISCUSSION/CONCLUSION

Change Order No. 61 is necessary to reconcile or balance line item quantities, overruns and underruns. These are items that are typically paid as measured in place. The item amount listed in the plan set is an estimated quantity. Final payment is based upon the field measured quantity for any particular line item. Items that measure greater than the estimated plan quantity are referred to as overruns, and items that measure less than the estimated plan quantity are referred to as underruns. This will reconcile the majority of the items on this project, except for those still under negotiation with the contractor and TxDOT. Approval of this action is necessary as one of the remaining requirements to close out the project and comply with the terms of the associated contract. Approval of this action reconciles actual quantities utilized in the construction of the project throughout the course of its more than three-year construction time period. Failure to approve this action will most likely lead to contractual claims under the terms of the associated contract between ...