File #: PH-15-028A    Version: 1 Name: Killeen-Ft Hood Regional Trail (Segment 3)
Type: Resolution/Public Hearing Status: Passed
File created: 6/10/2015 In control: City Council
On agenda: 7/14/2015 Final action: 7/14/2015
Title: Consider a memorandum/resolution authorizing the award of Bid No. 15-16 for a construction contract to RM Rodriguez Construction, LP for the Killeen Fort Hood Regional Trail (Segment 3) project.
Sponsors: Public Works Department, Transportation Division
Indexes: Hike & Bike Trail
Attachments: 1. Council Memorandum, 2. Engineer Award Recommendation Letter, 3. Bid Tabulation
Related files: DS-15-011, RS-16-152
TITLE

Consider a memorandum/resolution authorizing the award of Bid No. 15-16 for a construction contract to RM Rodriguez Construction, LP for the Killeen Fort Hood Regional Trail (Segment 3) project.

SUMMARY

AGENDA ITEM

AUTHORIZE THE AWARD OF A CONSTRUCTION CONTRACT (BID 15-16) TO RM RODRIGUEZ CONSTRUCTION, LP FOR THE CONSTRUCTION OF THE KILLEEN FORT HOOD REGIONAL TRAIL (SEGMENT 3) PROJECT.

ORIGINATING DEPARTMENT

PUBLIC WORKS - TRANSPORTATION DIVISION

BACKGROUND INFORMATION

In cooperation with the Federal Highway Administration, the Texas Highway Commission issued a call for project nominations for the statewide Transportation Enhancement Program (TE) on August 30, 2012. The call began on September 14, 2012, and closed on November 16, 2012. In two previous project calls, the City of Killeen (COK) had secured funding for two (2) hike and bike trails. Those projects (CCM/R 12-091R) have been extremely successful and beneficial to the City of Killeen.

On July 26, 2013, the City received notification that it had been selected to receive $1,455,498 for a TE award. The City of Killeen's proposed project ranked fourth out of 81 prospective projects submitted to the Texas Department of Transportation (TxDOT). On February 11, 2014, the City Council authorized a reimbursement resolution (CCM/R 14-023R) which included funding for the Westside Trail (Killeen Fort Hood Regional Trail Segment 3) project. On March 25, 2014, City Council authorized entering in an advance funding agreement (CCM/R 14-035R) with TxDOT for the TE award as documented by the Transportation Enhancement Program.

DISCUSSION/CONCLUSION

The City advertised for bids on April 19, April 26, and May 3, 2015. On May 21, 2015, bids were opened and read aloud for the construction of the project. There were four (4) bids submitted for the project: RM Rodriguez Construction, LP, of Temple, in the amount of $2,109,000.00; Westar Construction, Inc., of Georgetown, in the ...