Legistar header
                                                         
File #: PH-15-014    Version: 1 Name: Fund 343 Budget Amendment for Stagecoach Phase II and Elms Road Extension.
Type: Ordinance/Public Hearing Status: Passed
File created: 2/17/2015 In control: City Council
On agenda: 3/10/2015 Final action: 3/10/2015
Title: HOLD a public hearing and consider an ordinance amending the FY 2015 Annual Budget and Plan of Municipal Services of the City of Killeen by increasing Certificate of Obligation 2011 fund accounts by $486,503 to finance Stagecoach Road Reconstruction Phase II and Elms Road Extension.
Sponsors: Public Works Department, Transportation Division, Finance Department
Attachments: 1. Council Memorandum, 2. Ordinance
Related files: RS-16-130
TITLE

HOLD a public hearing and consider an ordinance amending the FY 2015 Annual Budget and Plan of Municipal Services of the City of Killeen by increasing Certificate of Obligation 2011 fund accounts by $486,503 to finance Stagecoach Road Reconstruction Phase II and Elms Road Extension.

SUMMARY

AGENDA ITEM

Budget Amendment for Stagecoach Road Reconstruction Phase II and Elms Road Extension

ORIGINATING DEPARTMENT

Finance

BACKGROUND INFORMATION

Various projects are funded through the Capital Improvement Program (CIP). The CIP is funded through the issuance of revenue bonds, general obligation bonds and certificates of obligation and can be used only for purposes outlined in the bond covenant.

In July 2013, the council approved staff recommendation to award a contract to McLean Construction for the Stagecoach Road Reconstruction Phase II (CCMR 13-087R).
In October 2014, the council approved staff recommendation to award a contract to Gary W. Purser Construction for the Elms Road Extension Project (CCMR 14-139R).

DISCUSSION/CONCLUSION

The City of Killeen approves the CIP budget along with the Annual Budget and Plan of Municipal Services in September each year. Although staff provides estimates based upon the best information at the time, the budget needs to be amended periodically as more accurate information becomes available. Changes in scope, schedules, and the project having remaining funds due to favorable bids or not enough funds due to unforeseen events require that a budget amendment be approved by City Council.

Additional funds are needed to cover contingency-related expenditures and change orders for the Stagecoach Road Reconstruction and Elms Road Extension projects.

FISCAL IMPACT

Unspent interest earnings from several older bond funds will be utilized to finance this project and have been transferred into Fund 343 via a residual equity transfer approved by the Council on October 21, 2014. Elms Road projec...

Click here for full text