File #: RS-23-192    Version: 1 Name: Amendment to Agreement with Garver LLC
Type: Resolution Status: Passed
File created: 10/26/2023 In control: City Council
On agenda: 11/28/2023 Final action: 11/28/2023
Title: Consider a memorandum/resolution approving Amendment No. 1 for the Taxiway B Rehabilitation Professional Services Agreement with Garver, LLC, in the amount of $269,200.
Sponsors: Aviation Department
Attachments: 1. Agreement, 2. Amendment, 3. Certificate of Interested Parties, 4. Presentation
Title

Consider a memorandum/resolution approving Amendment No. 1 for the Taxiway B Rehabilitation Professional Services Agreement with Garver, LLC, in the amount of $269,200.

Summary

DATE: November 14, 2023

TO: Kent Cagle, City Manager

FROM: Mike Wilson, Executive Director of Aviation

SUBJECT: Amendment No. 1 to the Professional Services Agreement with Garver LLC-Taxiway B Rehabilitation Project

BACKGROUND AND FINDINGS:

On August 23, 2022, the City Council awarded a Professional Services Agreement to Garver LLC for the Taxiway B Rehabilitation Project for the construction administration services, on-site resident project representative services, materials testing services, and project closeout services for this project at Killeen Regional Airport.

Amendment No. 1 adds professional services for this project. The original professional services during construction were based on the original contract time. This contract amendment adds additional Construction Administration Services and Construction Resident Project Representative (RPR) Observation for the extended construction time due to delays in construction and additional signage replacement adding to the construction scope of work via change order. This change will increase the construction duration by 168 calendar days. The original contract services were estimated based on a 250-calendar day construction duration (for substantial completion). This Amendment increases services estimated based on a 418-calendar day construction duration.

THE ALTERNATIVES CONSIDERED:

1. Do not approve Amendment No. 1 to Garver LLC's Agreement
2. Approve Amendment No. 1 to Garver LLC's Agreement

Which alternative is recommended? Why?

Alternative No. 2 is recommended because:
1. The FAA requires professional experienced oversite and documentation of the construction process.
2. Project is fully funded through an Airport Improvement Program (AIP) grant and Passenger Facility Charge (PFC) funds with no impact to the...