File #: RS-20-043    Version: 1 Name: Central Fire Station Dormitory Remodel
Type: Resolution Status: Passed
File created: 4/6/2020 In control: City Council
On agenda: 4/28/2020 Final action: 4/28/2020
Title: Consider a memorandum/resolution awarding Bid No. 20-01 for a construction contract with Hawk Builders, LLC in the amount of $302,400 to construct the Central Fire Station Dormitory Remodel project.
Sponsors: Public Works Department, Finance Department, City Attorney Department
Attachments: 1. Staff Report, 2. Bid Proposal, 3. Recommendation Letter, 4. Certificate of Interested Parties, 5. Presentation
TITLE

Consider a memorandum/resolution awarding Bid No. 20-01 for a construction contract with Hawk Builders, LLC in the amount of $302,400 to construct the Central Fire Station Dormitory Remodel project.

SUMMARY

DATE: April 28, 2020

TO: Kent Cagle, City Manager

FROM: Danielle Singh, Executive Director of Public Works

SUBJECT: Authorize the award of a construction contract with Hawk Builders, LLC in the amount of $302,400 to construct the Central Fire Station Dormitory Remodel project


BACKGROUND AND FINDINGS:

Built in 1976, the Central Fire Station has been in desperate need of an upgrade for many years. The dormitory area has communal living spaces with no separation between the beds for privacy. The scope of improvements under this project includes creating individual sleeping quarters, renovated bunk rooms, an office space, and small gym area in a separate room with outside access. Also, included is an IT closet to provide IT service to each quarter and throughout the dormitory area. Necessary mechanical, electrical, and plumbing improvements are part of this project.

On March 25, 2020, bids were opened and read aloud for the construction works of Central Fire Station Dormitory Remodel. Two contractors submitted bids for this project. The bids are as follows:

BIDDERS BID Amount
Aycock Construction, Inc $ 387,000
Hawk Builders, LLC $ 302,400

THE ALTERNATIVES CONSIDERED:

Alternatives are -
1) Do not move forward with the dormitory remodel at this time; or
2) Award a construction contract to Hawk Builders, LLC for the construction of the Central Fire Station Dormitory Remodel project in the amount of $ 302,400.

Which alternative is recommended? Why?

Alternative 2 is recommended because the remodel of the dormitory area at the Central Fire Station is needed and was designated as a pri...

Click here for full text