File #: RS-15-073    Version: 1 Name: Killeen Community Center Renovation
Type: Resolution Status: Passed
File created: 9/1/2015 In control: City Council
On agenda: 10/20/2015 Final action: 10/20/2015
Title: Consider a memorandum/resolution awarding Bid No. 15-27 for a construction contract with Vanguard Contractors, LP, for the renovation of the Killeen Community Center.
Sponsors: Parks and Recreation Department, Killeen Parks & Recreation
Indexes: Killeen Community Center
Attachments: 1. Council Memorandum, 2. Vanir Bid Recommendation Letter, 3. Standard Contract Agreement, 4. General Conditions Contract, 5. Supplemental Conditions Contract
TITLE

Consider a memorandum/resolution awarding Bid No. 15-27 for a construction contract with Vanguard Contractors, LP, for the renovation of the Killeen Community Center.

SUMMARY

AGENDA ITEM

PROFESSIONAL SERVICES CONTRACT FOR THE RENOVATION OF THE KILLEEN COMMUNITY CENTER

ORIGINATING DEPARTMENT

COMMUNITY SERVICES

BACKGROUND INFORMATION

The Killeen Community Center was constructed in 1973. The facility features a gymnasium, fitness room, and four meeting rooms that are available to the general public for meeting space. In addition, the facility houses the Volunteer Services Division and a component of Parks and Recreation. In recent years, funds have been utilized for the renovation of seven office spaces in the facility. These renovations enabled the relocation of Volunteer Services to the Community Center. Funds were also utilized for the replacement of the roof at the facility; however, over 50% of the facility has yet to be renovated. The heating, ventilation, and cooling (HVAC) system at the facility is in need of replacement, with the current system functioning in less than 50% of the facility. Safety hazards have been identified related to the support system for the basketball goals. The facility has numerous issues related to the American with Disabilities Act (ADA). In addition, the facility’s restrooms are in need of significant upgrades.

The Capital Improvement Bond Election of 2002 authorized funding specifically for renovating the Killeen Community Center.

In February 2014, the City Council authorized the City Manager to enter into a professional services contract with Vanir Construction Management, Inc. for the oversight of the design, bid, and remodel of the Killeen Community Center. In October 2014, City Council authorized the City Manager to enter into a professional services contract with L.S. Johnston Architects for the design work a...

Click here for full text