File #: RS-26-160    Version: 1 Name: Change Order #1 for Parks Maintenance, Fleet, Police Evidence Storage CIP
Type: Resolution Status: Resolutions
File created: 9/9/2026 In control: City Council
On agenda: 10/8/2026 Final action:
Title: Consider a memorandum/resolution authorizing Change Order No. 1 for the Parks Maintenance, Fleet Maintenance, and Police Evidence Storage Building Projects with CORE Construction in the amount of $1,741,508.00.
Sponsors: Engineering
Attachments: 1. Proposal, 2. Resolution 25-116R, 3. Change Order 1, 4. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title

Consider a memorandum/resolution authorizing Change Order No. 1 for the Parks Maintenance, Fleet Maintenance, and Police Evidence Storage Building Projects with CORE Construction in the amount of $1,741,508.00.

Body

DATE: October 8, 2026

TO: Kent Cagle, Interim City Manager

FROM: Andrew Zagars, P.E., City Engineer

SUBJECT: Authorize Change Order No. 1 with CORE Construction for the Parks Maintenance, Fleet Maintenance, and Police Evidence Storage Building Projects

BACKGROUND AND FINDINGS:

The fiscal year (FY) 2023 Capital Improvement Plan includes the Parks Maintenance, Fleet Maintenance, and PD Evidence Warehouse expansion, as funded projects for design and construction. On July 15, 2025, the City Council approved a design-build contract with CORE Construction, for the design and construction in the amount of $23,890,278.00 (CCMR25-116).

Change Order #1 is an increase in the project costs of $1,741,508.00 for the Parks Maintenance Building due to an increase in the building size to meet current and future needs, the replacement of a brick sanitary sewer manhole, and remediation of asbestos and lead materials that were found in the existing building.

The total increase for Change Orders No. 1 is $1,741,508.00 which equates to a 7.3% increase to the original contract.

THE ALTERNATIVES CONSIDERED:

N/A

Which alternative is recommended? Why?

N/A

CONFORMITY TO CITY POLICY:

This item conforms to State and Local policies.

FINANCIAL IMPACT:

What is the amount of the revenue/expenditure in the current fiscal year? For future years?

The total amount of Change Order No. 1 is an increase in the contract in the amount of $1,741,508.00.

Is this a one-time or recurring revenue/expenditure?

This is a one-time expenditure.

Is this revenue/expenditure budgeted?

Yes

If not, where will the money come from?

N/A

Is there a sufficient amount in the budgeted line-item for this revenue/expenditure?

Yes, $1,741,508 is available in the Certificates of...