File #: RS-24-035    Version: 1 Name: Consider authorizing a memorandum/resoluton for the Design Contract of the Community Center Roof Repair with Engineered Exteriors, LLC, in the amount of $69,600.00
Type: Resolution Status: Passed
File created: 1/18/2024 In control: City Council
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Consider a memorandum/resolution authorizing a professional services agreement with Engineered Exteriors, LLC, for the design and construction support of the Community Center Roof Replacement, in the amount of $69,600.00.
Sponsors: Development Services
Attachments: 1. Proposal, 2. Letter of Agreement, 3. Certificate of Insurance, 4. Contract Verification Form, 5. Certificate of Interested Parties, 6. Presentation
Title

Consider a memorandum/resolution authorizing a professional services agreement with Engineered Exteriors, LLC, for the design and construction support of the Community Center Roof Replacement, in the amount of $69,600.00.

Body

DATE: February 20, 2024

TO: Kent Cagle, City Manager

FROM: Edwin Revell, Executive Director of Development Services

SUBJECT: Authorize a professional services agreement with Engineered Exteriors, LLC, for the design and construction support of the Community Center Roof Replacement, in the amount of $69,600.00.

BACKGROUND AND FINDINGS:

The Community Center Roof Replacement project was included in the Capital Improvement Plan as a project in 2020 as a result of deficiencies found during a structural assessment of the Bob Gilmore Senior Center that occurred in 2019. This project includes expansion of the Rosa Hereford Community Center and remodeling of the existing floor space to accommodate and include the Senior Center needs that were once in the Bob Gilmer Senior Center.

On May 9, 2023, the City Council approved the contract, with HCS, Inc., for the expansion and renovation of the Community Center, in the amount of $7,416,835.00. This scope did not include full roof replacement for the existing Community Center. Upon review of the project, and during the demolition of the interior, it was discovered that the roof replacement for the existing roof is needed now. This full roof replacement would help to ensure that the ongoing remodeling work would be covered under warranty.
To expedite the needed roof replacement work, the city must engage a designer to provide the necessary roof replacement design details, bidding, and construction support services needed to support HCS, Inc. Consequently, City staff has negotiated a professional services Letter of Agreement with Engineered Exteriors, LLC, for the design and support of the Community Center Roof Replacement project, in the amount of $69,600.00.

THE ALTERNATIVES CONS...