File #: RS-20-046    Version: 1 Name: Waterline Rehab Phase 3 Award
Type: Resolution Status: Passed
File created: 4/20/2020 In control: City Council
On agenda: 5/12/2020 Final action: 5/12/2020
Title: Consider a memorandum/resolution awarding Bid Number 20-05 for construction of the Waterline Rehabilitation Phase III project to TTG Utilities, LP., in an amount not to exceed $2,059,264.50.
Sponsors: Public Works Department, Finance Department, City Attorney Department
Attachments: 1. Staff Report, 2. Bid Proposal, 3. Bid Receipt Summary, 4. Letter of Recommendation, 5. Location Map, 6. Certificate of Interested Parties, 7. Presentation
TITLE

Consider a memorandum/resolution awarding Bid Number 20-05 for construction of the Waterline Rehabilitation Phase III project to TTG Utilities, LP., in an amount not to exceed $2,059,264.50.

SUMMARY

DATE: May 12, 2020

TO: Kent Cagle, City Manager

FROM: Danielle Singh, Executive Director of Public Works

SUBJECT: Authorize the Award of a Construction Contract with TTG Utilities, LP in the amount of $2,059,264.50 to construct the Waterline Rehabilitation Phase III Project

BACKGROUND AND FINDINGS:

The 2012 Water and Wastewater Master Plan includes project 9W to rehabilitate or replace old, small diameter undersized waterlines in the northwest corner area of Killeen. The rehabilitation/replacement of these waterlines will help eliminate the number of waterline breaks, increase available fire flow, and improve water quality in this area.

The bid package was prepared with the base bid for waterlines with the highest priority of replacement and several Add Alternates were included in the bid package so that additional waterlines could be installed based on proposed cost and available funding. The base bid consists of approximately 5,000 feet of 8” waterline and approximately 13,500 feet of 6” waterline and associated fire hydrants, valves, fittings etc. along 13 different streets within the area bordered by W. Rancier Ave, Williamson Dr., and Garth Dr. Add Alternate No. 1 consists of approximately 700 feet of 6” waterline along Whitlow Dr. Add Alternate No. 2 consists of approximately 5,000 feet of 6” and 8” Waterline located on Valley Rd., Kern Rd., and Garth Dr.

On March 25th, the City of Killeen received competitive bids from four contractors for the Waterline Rehabilitation Phase III project. The bids are as follows:

BIDDERS BID (Base + Alt. 1+Alt. 2)
TTG Utilities, LP. 2,059,264.50
Atlas Construction Corp. 3,016,440.00
Bruce Flanigan Construction, Inc. 3,270,683....