File #: RS-24-142    Version: 1 Name: Contract Award Bid No. 24-31
Type: Resolution Status: Passed
File created: 7/8/2024 In control: City Council
On agenda: 8/20/2024 Final action: 8/20/2024
Title: Consider a memorandum/resolution awarding Bid Number 24-31 to TTG Utilities, Inc., for the Taxiway E Relocation Project at Killeen Regional Airport, in the amount of $6,844,245.
Sponsors: Aviation Department
Attachments: 1. Recommendation of Award and Bid Tab, 2. Contract, 3. Certificate of Interested Parties, 4. Presentation
Title

Consider a memorandum/resolution awarding Bid Number 24-31 to TTG Utilities, Inc., for the Taxiway E Relocation Project at Killeen Regional Airport, in the amount of $6,844,245.

Body

DATE: August 20, 2024

TO: Kent Cagle, City Manager

FROM: Mike Wilson, Executive Director of Aviation

SUBJECT: Award Bid No. 24-31 Taxiway E Relocation at Killeen Regional Airport

BACKGROUND AND FINDINGS:

A portion of Taxiway E at the Killeen Regional Airport needs rehabilitation. However, due to changes in Federal Aviation Administration (FAA) taxiway design standards, any rehabilitation to this taxiway requires relocation.
The City applied for and received an FAA Airport Improvement Program (AIP) grant for the design phase of this project. The project design is complete, and bids have been received. The construction phase of this project will be funded through a combination of funding from the FAA AIP, FAA Discretionary funds, a Community Project Funding grant supported by Congressman Pfluger and the match will come from the Passenger Facility Charge (PFC) Fund.
Advertising began on May 12, 2024, and appeared in the local newspaper as well as the City's website. Additionally, it was advertised on multiple statewide electronic bidding sites. A pre-bid meeting was held on May 21, 2024 with five (5) general contractors and two (2) sub-contractors attending.
Bids were opened on June 12, 2024, and the City of Killeen received three (3) bids as follows:
Bidders
Gage & Cade Co., LLC
TTG Utilities, Inc.
Zachry Construction
Bid Schedule A
$5,432,557.11
$5,918,195.00
$7,910,141.91
Additive Alt 1
$1,244,959.40
$926,050.00
$1,071,214.10
Total
$6,677,516.51
$6,844,245.00
$8,981,356.01

A thorough review of each bid package was completed by the airport's consultant and staff and one bidder, Gage & Cade Construction, LLC, was disqualified for an incomplete bid due to an incomplete Bid Form, incomplete DBE documentation, and insufficient Good Faith Efforts (GFE).
The lowest r...