Legistar header
                                                         
File #: RS-19-016    Version: 1 Name: South Water Supply, Phase 1: Lower Pressure Plane Water Main
Type: Resolution Status: Passed
File created: 1/18/2019 In control: City Council
On agenda: 2/12/2019 Final action: 2/12/2019
Title: Consider a memorandum/resolution awarding Bid No. 19-16 for the construction of the South Water Supply Project, Phase 1: Lower Pressure Plane Water Main to Gary W. Purser Construction Ltd.
Sponsors: Public Works Department, Engineering
Attachments: 1. Staff Report, 2. Bid Recommendation Letter, 3. Bid Proposal, 4. Certificate of Interested Parties, 5. Presentation
Related files: RS-18-109, RS-23-025
TITLE

Consider a memorandum/resolution awarding Bid No. 19-16 for the construction of the South Water Supply Project, Phase 1: Lower Pressure Plane Water Main to Gary W. Purser Construction Ltd.

SUMMARY

DATE: February 5, 2019

TO: Ronald L. Olson, City Manager

FROM: David A. Olson, Executive Director of Public Works

SUBJECT: Authorize the award of a contract to Gary W. Purser Construction Ltd. to construct the South Water Supply Project, Phase 1: Lower Pressure Plane Water Main

BACKGROUND AND FINDINGS:

Bell County Water Control and Improvements District No. 1 (WCID #1) is currently building a new water treatment plant at Stillhouse Hollow Lake and a large transmission main to deliver 10 MGD of treated water to the City of Killeen (City). This project has an estimated completion date of Spring 2020. The WCID #1 water transmission main will end near the intersection of Trimmier and Chaparral. The City needs to provide the infrastructure to deliver this water from that location to the City’s current water distribution system. WCID #1 has requested that this infrastructure include an elevated ground storage tank. The 2012 Water and Wastewater Master Plan includes four projects in this area to store treated water from WCID #1, deliver water to the lower and upper pressure planes, and pump additional water into the upper pressure plane.

On February 14, 2017, Freese & Nichols, Inc. (FNI) was awarded a Professional Service Agreement to design the South Water Supply Project (SWS). Their agreement included the design, bid and construction management services for a 3 MG elevated ground storage tank, an 8 MGD pump station, approximately 32,100 LF of 20-inch and 30-inch pipeline, and associated appurtenances. The construction of the SWS project is divided into a total of four (4) Phases. The work represented by this bid and recommended to award for construction is Phase 1: approximately 3,000 linear feet of 20-inch water line along the South side of Chapa...