Legistar header
                                                         
File #: RS-24-055    Version: 1 Name: Consider a memorandum/resolution authorizing a professional services agreement with Scheibe Consulting, LLC in the amount of $360,000 for the Drainage Master Plan Project
Type: Resolution Status: Passed
File created: 1/18/2024 In control: City Council
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Consider a memorandum/resolution authorizing a professional services agreement with Scheibe Consulting, LLC, for the Drainage Master Plan Project, in the amount of $360,000.
Sponsors: Development Services
Attachments: 1. Agreement, 2. Certificate of Insurance, 3. Contract Verification Form, 4. Certificate of Interested Parties, 5. Presentation
Title

Consider a memorandum/resolution authorizing a professional services agreement with Scheibe Consulting, LLC, for the Drainage Master Plan Project, in the amount of $360,000.

Body

DATE: March 19, 2024

TO: Kent Cagle, City Manager

FROM: Edwin Revell, Executive Director of Development Services

SUBJECT: Authorize the execution of a Professional Services Agreement with Scheibe Consulting LLC, for the Drainage Master Plan Project in the amount of $360,000

BACKGROUND AND FINDINGS:

This project was included in the FY 2022 Capital Improvement Plan because of the need to update the existing 2012 Master Drainage Plan. Since 2012, several drainage improvements projects have been completed, new growth and land development have occurred throughout the city, and drainage standards have changed.

The City's current plan has not been updated since 2012. The drainage program needs updating to conform with current design standards and methodologies in order to provide guidance for capital projects throughout the city. Additionally, the current engineering standards needs to be updated to meet current methodologies, standards, and MS4 permit requirements.

This contract will be cover phase one of the new Drainage Master Plan. This phase includes reviewing the existing drainage plan, updating existing engineering rainfall and runoff models, and using this information as a basis for updating existing drainage standards, developing potential drainage improvement projects, and for preparing future FEMA grant project applications.

Staff reviewed several proposals and chose Scheibe Consulting LLC, for an amount not to exceed $360,000 to perform this service. All project efforts are expected to be completed within 12 months after final project contract execution.

THE ALTERNATIVES CONSIDERED:

N/A

Which alternative is recommended? Why?

N/A

CONFORMITY TO CITY POLICY:

This item conforms to state and local policies.

FINANCIAL IMPACT: