Title
Consider a memorandum/resolution awarding Bid No. 25-22, Stagecoach Reconstruction Phase 1, to JHL Construction, in the amount of $7,716,902.72.
Body
DATE: April 1, 2025
TO: Kent Cagle, City Manager
FROM: Andrew Zagars, P.E., City Engineer
SUBJECT: Authorize the award of Bid No. 22, Stagecoach Reconstruction Phase 1 to JHL Construction in the amount of $7,716,902.72
BACKGROUND AND FINDINGS:
The Stagecoach Reconstruction Phase 1 project was included in the Street Reconstruction Bond in Fiscal Year 2022 as a result of the previous pavement management program that prioritized streets needing replacement. The pavement condition of Stagecoach showed that the road degraded to such an extent that the solution to repair the road, in the most economically way, was full replacement.
The project includes replacement of the roadway between East Trimmier Road and W.S. Young Drive.
Pape Dawson provided professional services for the design and bidding for this project. All received bids were opened on February 20, 2025, and read aloud through Zoom online video conferencing and are noted below:
Bidders
Total Bid Amount
BP3 Earthwork, LLC
$8,386,379.96
Cash Construction Company, Inc.
$8,579,577.00
CK Newberry, LLC
$9,604,868.53
JHL Construction
$7,716,902.72
Texas Materials Group
$7,907,332.30
TTG Utilities
$8,064,041.33
THE ALTERNATIVES CONSIDERED:
N/A
Which alternative is recommended? Why?
N/A
CONFORMITY TO CITY POLICY:
The project conforms to all State and City purchasing policies.
FINANCIAL IMPACT:
What is the amount of the revenue/expenditure in the current fiscal year? For future years?
The total cost for the construction of the Stagecoach Road Reconstruction Phase 1 Project is $7,716,902.72.
Is this a one-time or recurring revenue/expenditure?
This is a one-time expenditure.
Is this revenue/expenditure budgeted?
The project is partially funded in the 2022 Bond and Governmental CIP Funds. The remaining budget will be appropriated on the m...
Click here for full text