Title
Consider a memorandum/resolution authorizing Change Order No. 1 for the Stagecoach Reconstruction Phase 1 Project with JHL Construction, resulting in a contract decrease in the amount of $71,252.52.
Body
DATE: December 1, 2026
TO: Dr. Peoples, City Manager
FROM: Andrew Zagars, P.E., City Engineer
SUBJECT: Change Order No. 1 for the Stagecoach Reconstruction Phase 1 Project with JHL Construction
BACKGROUND AND FINDINGS:
The FY 2022 Capital Improvement Program included the Stagecoach Reconstruction Project, as funded projects for design and construction. On April 1, 2025, the City Council approved a construction contract with JHL Construction, for the construction of Phase 1 of the Stagecoach Reconstruction Project in the amount of $7,716,902.72 (CCMR25-042).
Change Order No. 1 represents the final change order for the project needed for the project close-out. The change order adjusts the contract to reflect actual quantities used during construction, resulting in a net decrease of $71,252.52, or approximately 0.9% of the original contract amount. The overall changes in quantities reflect a change in the quantiles of items such as a reduction in the lime treatment area amount, and elimination of existing traffic markings and striping that was a result of the lane closure to expedite the project completion. Net increases include asphalt, testing, and temporary striping that would have been used for an the additional phase of construction if we were to keep both lanes of traffic open at all times.
Upon approval, the revised construction contract amount will be $7,645,650.20.
THE ALTERNATIVES CONSIDERED:
Which alternative is recommended? Why?
Click or tap here to enter text.
CONFORMITY TO CITY POLICY:
This item conforms to State and Local policies.
FINANCIAL IMPACT:
What is the amount of the revenue/expenditure in the current fiscal year? For future years?
Change Order No. 1 will decrease the existing construction contract by $71,252.52, reducing the total contract amount from $7,716,902.72 to $7,645,650.20. The decrease reflects adjustments to final construction quantities and does not represent additional revenue or expenditure.
Is this a one-time or recurring revenue/expenditure?
This is a one-time reduction in the existing construction contract.
Is this revenue/expenditure budgeted?
Yes. The project is included in the approved Capital Improvement Program and is funded through the Street Maintenance Fund (Fund 225).
If not, where will the money come from?
N/A
Is there a sufficient amount in the budgeted line-item for this revenue/expenditure?
N/A. Change Order No. 1 reduces the existing construction contract by $71,252.52. The reduction will release previously committed funding within the Street Maintenance Fund, CIP project account 225-56201-900-400-923012.
RECOMMENDATION:
Staff recommends that the City Council authorize the City Manager, or designee, to execute Change Order No. 1 with JHL Construction, for the Stagecoach Reconstruction Project, Phase 1, decreasing the construction contract in the amount of $71,252.52, for a revised total contract amount of $7,645,650.20.
DEPARTMENTAL CLEARANCES:
Engineering Services
Finance
City Attorney
ATTACHED SUPPORTING DOCUMENTS:
Change Order 1
Resolution 25-042R
Presentation