File #: RS-22-171    Version: 1 Name: Conder Park and AA Lane Park Drainage Improvement Project
Type: Resolution Status: Passed
File created: 11/1/2022 In control: City Council
On agenda: 12/6/2022 Final action: 12/6/2022
Title: Consider a memorandum/resolution awarding Bid No. 22-34, Conder Park and AA Lane Park Drainage Improvements Project, to Choice Builders, LLC in the amount of $597,113.
Sponsors: Development Services, Engineering
Attachments: 1. Bid Tabulation, 2. Letter of Recommendation, 3. Proposal, 4. Certificate of Interested Parties, 5. Presentation

Title

 

Consider a memorandum/resolution awarding Bid No. 22-34, Conder Park and AA Lane Park Drainage Improvements Project, to Choice Builders, LLC in the amount of $597,113.

 

Summary

 

DATE:                     November 29, 2022                     

 

TO:                     Kent Cagle, City Manager                     

 

FROM:                     Edwin Revell, Executive Direction of Development Services                     

 

SUBJECT:                     Authorize the award of Bid 22-34 to Choice Builders, LLC for the construction of the Conder Park and AA Lane Park Drainage Improvements Project in the amount of $597,113.00.                     

 

BACKGROUND AND FINDINGS:

 

This project was included in the 2012 Drainage Master Plan. The purpose is to make drainage improvements to channels, perform bank stabilization measures, make outfall improvements, and to construct a low water crossing to maximize the use of each park.

The MRB Group provided professional services for design and bids. Subsequently, the city published and received bids for the Conder Park and AA Lane Park Drainage Improvements Project on October 27th, 2022. The bids were opened and read aloud through zoom online video conferencing and are as follows:

 

Bidders

Total Bid Amount

Choice Builders, LLC

$597,113.00

HCS Inc.

$757,335.00

ERS Inc.

$1,213,002.00

 

 

THE ALTERNATIVES CONSIDERED:

 

1.                     Reject all bids and do not move forward with the construction of the Conder Park and AA Lane Park Drainage Improvements Project

2.                     Award Bid 22-34 to Choice Builders, LLC for the construction of the Conder Park and AA Lane Park Drainage Improvements Project in the amount of $597,113.00.

 

Which alternative is recommended? Why?

 

Alternative “2” is recommended because:

 

a.                     Choice Builders, LLC is the lowest responsible bidder.

b.                     The MRB Group, the design engineering firm on this project, reviewed and recommended the contract be awarded to Choice Builders, LLC, in the amount of $597,113.00.

 

CONFORMITY TO CITY POLICY:

 

This project conforms to all State and City purchasing policies.

 

FINANCIAL IMPACT:

 

What is the amount of the expenditure in the current fiscal year? For future years?

 

The total cost for construction of the Conder Park and AA Lane Park Drainage Improvements Project is $597,113.00.

 

Is this a one-time or recurring expenditure?

 

This is a one-time expenditure

 

Is this expenditure budgeted?

 

Yes, the funds are available in the Drainage Capital Improvement Fund account 375-8934-493.69-03.

 

If not, where will the money come from?

 

N/A

 

Is there a sufficient amount in the budgeted line-item for this expenditure?

 

Yes

 

RECOMMENDATION:

 

Staff recommends that the City Council award Bid 22-34 to Choice Builders Inc. for construction of the Conder Park and AA Lane Park Drainage Improvements Project in the amount of $597,113.00, authorize the City Manager or his designee to enter into a contract with Choice Builders LLC, and authorize the City Manager to execute any and all changes within the amounts set by state and local law.

 

DEPARTMENTAL CLEARANCES:

 

Development Services

Finance

City Attorney

 

ATTACHED SUPPORTING DOCUMENTS:

 

Bid Tabulation

Recommendation Letter

Bid Proposal

Certificate of Interested Parties