Legistar header
                                                         
File #: RS-23-100    Version: 1 Name: Consider a Memorandum/Resolution Awarding Bid No 23-21; E. Trimmier Road Bridge Repair
Type: Resolution Status: Passed
File created: 5/26/2023 In control: City Council
On agenda: 6/27/2023 Final action: 6/27/2023
Title: Consider a memorandum/resolution awarding Bid No. 23-21, E. Trimmer Road Bridge Repair, to JHL Construction, in the amount of $387,882.50.
Sponsors: Engineering , Development Services
Attachments: 1. Bid Proposal, 2. Consultant Recommendation Letter, 3. Contract Verification Form, 4. Certificate of Interested Parties, 5. Presentation
Title

Consider a memorandum/resolution awarding Bid No. 23-21, E. Trimmer Road Bridge Repair, to JHL Construction, in the amount of $387,882.50.

Summary

DATE: June 20, 2023

TO: Kent Cagle, City Manager

FROM: Edwin Revell, Executive Director of Development Services

SUBJECT: Authorize the award of Bid No. 23-21, E. Trimmer Road Bridge Repair, to JHL Construction in the amount of $387,882.50

BACKGROUND AND FINDINGS:

This project was included in the Capital Improvement Plan as a project in FY 2021 as a result of deficiencies found during a bridge inspection performed by TXDOT. It was found during the inspection that the southeast wingwall was separated and needed to be replaced due to the lack of support to the adjacent roadway. During the design of the project, it was also found that the northwest wingwall was starting to fail and needed to be replaced with this project.
The project includes replacement of both the northwest and southwest concrete wingwalls of the bridge. The project will also perform minor grading along the ditch and remove excess debris.
Freese and Nichols, Inc. provided professional services for design and bids. All received bids were opened and read aloud through zoom online video conferencing and are noted below.

Bidders
Total Bid Amount
JHL Construction
$387,882.50


THE ALTERNATIVES CONSIDERED:

1. Reject all received bids and do not move forward with the construction of the E. Trimmier Road Bridge Repair Project.
2. Award Bid 23-21, E. Trimmer Road Bridge Repair, to JHL Construction in the amount of $387,882.50.

Which alternative is recommended? Why?

Alternative 2 is recommended because:

a. JHL Construction is the lowest responsible bidder.
b. Friese and Nichols, Inc, the design engineering firm on this project, reviewed and recommended the contract be awarded to JHL Construction., in the amount of $387,882.50.

CONFORMITY TO CITY POLICY:

The project conforms to all State and City purchasing policies.