File #: RS-23-057    Version: 1 Name: Chamber of Commerce Emergency Repairs
Type: Resolution Status: Passed
File created: 2/22/2023 In control: City Council
On agenda: 3/28/2023 Final action: 3/28/2023
Title: Consider a memorandum/resolution ratifying the Letter of Agreement with TRSI, LLC dba Target Solutions for repairs to 1 Santa Fe Plaza, Killeen Texas due to a structure fire that occurred on December 6, 2022, in the amount of $87,891.17.
Sponsors: Community Development Department
Attachments: 1. Letter of Agreement, 2. Certificate of Interested Parties, 3. Presentation
Title

Consider a memorandum/resolution ratifying the Letter of Agreement with TRSI, LLC dba Target Solutions for repairs to 1 Santa Fe Plaza, Killeen Texas due to a structure fire that occurred on December 6, 2022, in the amount of $87,891.17.

Summary

DATE: March 21, 2023

TO: Kent Cagle, City Manager

FROM: Leslie Hinkle, Executive Director of Community Development

SUBJECT: Emergency Repairs related to 1 Santa Fe Plaza, Killeen Texas

BACKGROUND AND FINDINGS:

On December 6, 2022, there was a fire at 1 Santa Fe Plaza. The building is occupied by the Greater Killeen Chamber of Commerce and the building is a city asset. There was damage to the interior and the exterior of the historic structure (Santa Fe Railroad Depot). The City Manager authorized emergency repairs to take place effective December 7, 2022. The City's insurance carrier (TML) authorized and approved the scope of work to begin on the interior and that work has been completed. TML insurance approved the scope of work on the exterior of the building to also be completed. This work is under a separate scope since most of the exterior work that is required to be done in order to restore the historic features of the building.

TRSI, LLC dba Target Solutions has been contracted to perform the exterior work on the building and TML has approved the work to be completed. Target Solutions started the work in early February 2023 and the work is expected to take up to 120 days due to availability of building products that need to be milled and reproduced. TML has authorized the work to be completed in the amount of $87,891.17. City will receive insurance proceeds in this amount minus the city's $10,000 deductible.

THE ALTERNATIVES CONSIDERED:

1. Do not approve the ratification of Letter of Agreement for expenditures with Target Solutions for the emergency repairs to the building at 1 Santa Fe Plaza (Chamber of Commerce).
2. Approve the ratification of Letter of Agreement for expenditure...

Click here for full text