Legistar header
                                                         
File #: RS-23-038    Version: 1 Name: Contract Award-Corporate Hangar II Project
Type: Resolution Status: Passed
File created: 1/30/2023 In control: City Council
On agenda: 2/28/2023 Final action: 2/28/2023
Title: Consider a memorandum/resolution awarding Bid Number 23-06 for construction of the Corporate Hangar II project to Native American Services Corporation, in the amount of $5,335,019.32.
Sponsors: Aviation Department
Attachments: 1. Bids, 2. Contract, 3. Certificate of Interested Parties, 4. Presentation
Title

Consider a memorandum/resolution awarding Bid Number 23-06 for construction of the Corporate Hangar II project to Native American Services Corporation, in the amount of $5,335,019.32.

Summary

DATE: February 21, 2023

TO: Kent Cagle, City Manager

FROM: Mike Wilson, Executive Director of Aviation

SUBJECT: Authorize the Award of Bid No. 23-06, Corporate Hangar Phase II Project, to Native American Services Corporation.

BACKGROUND AND FINDINGS:

The Corporate Hangar Phase II project was originally bid in March 2022. In response, the City received three bids. However, the City was required to reject all bids due to a delay in receiving Federal Aviation Administration (FAA) grant funding.

On September 13, 2022, the City Council accepted a FAA Military Airport Program (MAP) grant in the amount up to $4,553,070 to fund eligible portions of the Corporate Hangar II Project at the Killeen-Fort Hood Regional Airport (KFHRA).

City staff re-advertised for bids for the project on November 6 and 13, 2022. Advertising appeared in the local newspaper as well as the City's website. Additionally, it was advertised on multiple statewide electronic bidding sites. A pre-bid meeting was held on November 15, 2022, with six (6) general contractors and various sub-contractors attending.

Bids were opened on December 8, 2022, and the City of Killeen received one (1) bid as follows:

NASCO
Base Bid A-Site Civil Improvements (Eligible) $1,451,143.35
Base Bid B-Hangar (Eligible) $2,387,187.00
Base Bid C-Interior Framing/Finish Out Office Space (Ineligible) $918,721.00
Additive Alternative 1-Lift Station Upgrades (Eligible) $70,841.97
Additive Alternative 2-2nd Floor Structure over Office Space (Ineligible) $176,296.00
Additive Alternative 3-Wet Pipe Sprinkler System (Eligible) $54,871.00
Additive Alternative 4-Hangar Bay Extension (Eligible) $275,959.00
Total $5,335,019.32