Legistar header
                                                         
File #: RS-22-171    Version: 1 Name: Conder Park and AA Lane Park Drainage Improvement Project
Type: Resolution Status: Passed
File created: 11/1/2022 In control: City Council
On agenda: 12/6/2022 Final action: 12/6/2022
Title: Consider a memorandum/resolution awarding Bid No. 22-34, Conder Park and AA Lane Park Drainage Improvements Project, to Choice Builders, LLC in the amount of $597,113.
Sponsors: Development Services, Engineering
Attachments: 1. Bid Tabulation, 2. Letter of Recommendation, 3. Proposal, 4. Certificate of Interested Parties, 5. Presentation
Title

Consider a memorandum/resolution awarding Bid No. 22-34, Conder Park and AA Lane Park Drainage Improvements Project, to Choice Builders, LLC in the amount of $597,113.

Summary

DATE: November 29, 2022

TO: Kent Cagle, City Manager

FROM: Edwin Revell, Executive Direction of Development Services

SUBJECT: Authorize the award of Bid 22-34 to Choice Builders, LLC for the construction of the Conder Park and AA Lane Park Drainage Improvements Project in the amount of $597,113.00.

BACKGROUND AND FINDINGS:

This project was included in the 2012 Drainage Master Plan. The purpose is to make drainage improvements to channels, perform bank stabilization measures, make outfall improvements, and to construct a low water crossing to maximize the use of each park.
The MRB Group provided professional services for design and bids. Subsequently, the city published and received bids for the Conder Park and AA Lane Park Drainage Improvements Project on October 27th, 2022. The bids were opened and read aloud through zoom online video conferencing and are as follows:

Bidders
Total Bid Amount
Choice Builders, LLC
$597,113.00
HCS Inc.
$757,335.00
ERS Inc.
$1,213,002.00


THE ALTERNATIVES CONSIDERED:

1. Reject all bids and do not move forward with the construction of the Conder Park and AA Lane Park Drainage Improvements Project
2. Award Bid 22-34 to Choice Builders, LLC for the construction of the Conder Park and AA Lane Park Drainage Improvements Project in the amount of $597,113.00.

Which alternative is recommended? Why?

Alternative "2" is recommended because:

a. Choice Builders, LLC is the lowest responsible bidder.
b. The MRB Group, the design engineering firm on this project, reviewed and recommended the contract be awarded to Choice Builders, LLC, in the amount of $597,113.00.

CONFORMITY TO CITY POLICY:

This project conforms to all State and City purchasing policies.

FINANCIAL IMPACT:

What is the amount of the expenditure in the current fiscal year? For fut...